How long does it take to build a website? Honest timelines (2026)
Real-world timelines for small business websites in Australia: landing page, brochure site and online store, what makes projects drag, and the one thing that doubles every schedule: missing content.
3 min read
In short: with a professional and a normal small-business scope, a focused landing page takes one to two weeks, a four-to-six-page brochure site two to three weeks, and an online store two to four weeks. DIY on a site builder takes anywhere from a weekend to three months of abandoned drafts, and agencies quote six to twelve weeks for the same scope because more people touch it. The thing that actually sets the schedule is rarely the building: it is how fast the words, photos and decisions arrive. A build with content ready moves three times faster than a build waiting on it.
I build sites for Melbourne small businesses and makers, so these are working numbers from real projects, not theory.
Honest timelines by project type
- Landing page, one to two weeks. One sharp page: who you are, the work, one clear next step. A week of building, a few days of polish and review.
- Brochure site (four to six pages), two to three weeks. Home, about, work, services, contact. The extra time is mostly content: each page needs real words and real images.
- Online store, two to four weeks. The storefront is the visible half; configuring products, variants, shipping, GST and the order admin properly is the invisible half that sets real stores apart. More products, more time.
- Custom or bespoke build, four to eight weeks. When the brand and the site are designed together from scratch, the design conversation rightly takes its share; the bespoke process shows how I run it.
Where you sit inside each range depends on revision rounds and on the next section.
What actually makes projects drag
After enough projects the pattern is clear. It is almost never the code.
- Missing content. The site is built and sits waiting for the about text, the product photos, the price list. This is the number one schedule killer everywhere, and it is why I scope content before building starts.
- No decider. When three people must agree on every shade of green, weeks appear from nowhere. One owner with taste beats a committee.
- Scope creep. "While you're in there, can we add a booking system?" New scope is fine; pretending the date holds is not.
- Slow feedback loops. A build that gets answers in a day finishes weeks before the one that gets answers on Sundays.
None of these are character flaws, but a realistic schedule budgets for them, and a good builder tells you that up front instead of quoting a fantasy date.
How to make your own build fast
Have the raw content ready before kick-off: rough words beat no words, phone photos beat no photos. Name one decision-maker. Answer within a couple of days. Do that and the short end of every range above is yours; my fastest builds were fast because the client was, not because the code was different.
What it costs while we are being honest
Timelines and money belong in the same conversation: a website or portfolio site starts at $1,800 AUD, and an online store at $2,500 AUD, one-time. I also wrote a full breakdown of what a website costs in Melbourne. If you want both numbers for your actual project, the date and the dollars, tell me what you need and I will send a written scope and fixed quote.